Safety & separation

Fire-rated lift hoardings.

Robust, lockable working enclosures that separate lift works from building users and give engineers controlled access at every landing.

Built for the site

Secure protection without losing practicality.

Hoardings must do more than screen off an opening. They form the boundary between a live building and a high-risk work area.

We survey each landing, select the appropriate construction and coordinate access positions with the lift contractor before installation.

01 / CONSTRUCTION

Timber or modular solutions

Site-built or pre-made arrangements selected around the building, duration and fire-performance requirement.

02 / CONTROLLED ACCESS

Lockable engineer access

Fire-door or access-panel configurations with combination locks and practical routes to the lift opening.

03 / PROTECTION

Floor and fall protection

Protection to approach routes, working zones and secondary measures where required by the project.

04 / INTERFACES

Close fitting at every landing

Adapted around walls, nibs, cupboards, corridors and existing fire doors without unnecessary disruption.

05 / SIGNAGE

Clear work-zone information

Installation of supplied safety signage, controlled access information and clean external finishes.

06 / ALTERATIONS

Responsive during the works

Planned adjustments when installation sequences or access requirements change.

Hoarding sequence

Surveyed, installed and handed over.

  • Landing-by-landing measurements
  • Fire-rating and access requirements confirmed
  • Protection installed before disruptive works
  • Locks, doors and panels checked
  • Photographic and handover records completed